Posts Tagged ‘reserved lanes’

h1

Officials boost roads and “Super BRT”, put urban rail on side track

31 August 2017

Cross-section of one version of TxDOT’s plan for massive rebuild and expansion of I-35. Center tolled “express” lanes (at bottom center of diagram) are proposed for use by “Super BRT” project to be funded and operated by Capital Metro. Graphic: Mobility35. (Click to enlarge.)

Commentary by David Orr

David Orr, an Austin community activist involved with transportation issues, is a longtime environmental justice and transportation advocate.

Last month, on July 26th, Capital Metro’s Project Connect, together with several other regional agencies, sponsored another of their “Traffic Jam” community meetings to discuss possible options in the planning process. This mainly consisted of a panel of professionals and officials, some local, and some from elsewhere in the country, sitting on a stage in a chapel at Huston-Tillotson University explaining different transit issues to the audience.

I attended this event, but was extremely disappointed in what I saw for a number of reasons. For one, the talking heads were allowed to go over their allotted time (typical for politicians and agency officials), leaving only a half-hour of the two and a half hours of the originally scheduled event time for audience participation. This common practice is designed to minimize public input and maximize officials’ output (i.e., a PR effort).


Project Connect-sponsored “Traffic Jam” meeting on July 26th at Huston-Tillotson University. Opportunity for audience participation was truncated. Photo: L. Henry.


More importantly to our concerns, as was the case with the April “Traffic Jam”, the politicians never got specific about mass transit and talked instead mostly about how expensive transit is and how little money they have. At the same time they have been touting how much good they’re doing building new road capacity with the 2016 bond issue.

Capital Metro’s blog post on the recent “Traffic Jam” added little of substance, but in truth there was little offered by the consultants and local officials, so not much to report on. This event could have been much more effective had there been discussion of Austin’s specific needs, rather than dwelling on reports of what worked in other cities. There was no mention from the stage of what kind of new transit should be built here – and where. That was a glaring omission in the program agenda. It seemed a clear message that they’re seeking public (written) comment of the kind where officials will not be required to respond with any specificity, much less take a stand for or against. I hope I’m wrong, but to date the only messages we’ve received indicating openness to specific forms of new transit initiatives relate to what they’re calling “Super BRT” as if it were a done deal.

The “Super BRT” idea has been brought to public attention only within the last couple of months, bypassing Project Connect’s ongoing “high-capacity transit” study. A June 27th article by Caleb Pritchard in the Austin Monitor cited information from Capital Metro’s vice president of strategic planning and development, Todd Hemingson:

… Hemingson told reporters that the agency has been talking with TxDOT for five years about the I-35 bus rapid transit plan. The department is planning a $4 billion overhaul of the highway and appears to be open to the agency’s insistence that the project include some dedicated allowance for transit. The formative vision for the bus rapid transit system includes a handful of stations built on bus-only lanes in the median of the interstate. Those stations, Hemingson said, would be paired with frequent-service bus routes on intersecting east-west corridors.

This “Super BRT” is really a “pseudo BRT” plan, since the buses would run with mixed traffic in HOV toll lanes (“HOT lanes”). Basically, it seems like just another express bus system with some added improvements.

At the July 26th “Traffic Jam” I was particularly disturbed by a glossy brochure being distributed from Capital Metro titled Connections 2025, which laid out in very concrete terms the agency’s “vision” for the next five years. Nowhere in this document was any rail expansion even mentioned as a possibility. In contrast, the I-35 “Super BRT” plan was mentioned twice, in both places identifying it as if it’s already approved as a project in line for implementation.


Capital Metro’s Connections 2025 brochure includes “Super BRT” as an assumed project. Graphic: CMTA. (Click to enlarge.)


There was no discussion at all of this “Super BRT” project on I-35 during any of the many presentations and speeches during the program, and the very abbreviated public Q&A at the meeting did not permit me to ask for clarification. The only mention in this document of the Guadalupe-Lamar corridor was the continued development and expansion of MetroRapid 801 as well as 803 and additional routes. If they intend to continue to dump cash on the “rapid bus” projects in this corridor, that would effectively preclude serious discussion of a light rail transit (LRT) project in that corridor within the next decade at least.

In the Connections 2025 brochure, the “Super BRT” project was listed on the agency timeline for completion by 2023. Needless to say, it looks like the fix is in, at least as far as Capital Metro is concerned. However, I did ask a Project Connect staffer whether this was now a foregone conclusion, and he insisted it’s not. He also said that LRT is still on the table, but admitted that no one at the agency is really discussing it. That was an eye-opener.

Clearly this is a major challenge to those of us – transit advocates and a large contingent of neighborhoods and other community members – who have been backing LRT in Guadalupe-Lamar (G-L). Perhaps It’s time to request Capital Metro’s board for clarification on their plans for “Super BRT” and how their public input supports this major investment. Especially in view of the fact that this carries a huge opportunity cost for alternatives that might include LRT anywhere else in the city, much less on the G-L route. It’s clear that Capital Metro has been intentionally avoiding responding to the continuing public input they’re receiving in support of LRT and the lack of public support for this “Super BRT” notion.

It may also be necessary at some point to bypass Capital Metro and take this directly to the City Council. Council can make this happen even if they have to drag the transit agency off the “Super BRT” express bus.

However, there are other factors in play that may take the air out of the tires of this scheme. A July 24th article by Ben Wear in the American-Statesman quotes a TxDOT spokesperson regarding the request for money from Capital Metro for in-line stations on I-35. The TxDOT representative insists that “as far as financing goes, none of our funding sources will cover transit.”

Based on my reading of this news report, it seems TxDOT has given Capital Metro a clear signal that “Super BRT” will only happen if the transit agency pays for it. In the current situation, that’s actually very good news from the standpoint of proper planning and what kind of major transit improvement Austin truly needs – LRT.

If Capital Metro can’t raise the funds on its own to build this “Super BRT” – or even some scaled-back version of it – that will likely be the end of that bad dream. Presumably its proponents would have to get some bond money to fund it, but if that had to go before the voters it could turn out like the Prop 1 debacle which failed because the public support just wasn’t there. Capital Metro’s credibility would be pretty much destroyed. So maybe there is hope for a G-L LRT after all. From a politics standpoint, it’s usually easier to kill something controversial than it is to approve it.

A small but vocal opposition armed with facts could probably sink “Super BRT” if it came to a bond election. I suspect that politically aware members of Capital Metro’s board would be sensitive to sustained expressions of support for G-L LRT, and if there’s no evident support for Super BRT they may respond accordingly, if reluctantly.

We have every reason to doubt that Capital Metro will even be able to come close to providing the money demanded by TxDOT to build the “Super BRT” line, at least to whatever standards Capital Metro may determine will have a ghost of a chance in reaching reasonable ridership numbers. This would be a situation where the lack of agency funding could actually work to the benefit of truly effective transit – i.e., an urban rail alternative.

In any case, approval of G-L LRT will itself require a public vote. Nevertheless, supporters of this long-overdue project have good reason to believe it will pass if we can bring strong public support to the cause. We’ll have to win an election, and we need to start strategizing now.

My hunch is that funding “Super BRT” will kill off LRT for the next decade. Conversely LRT could do in this pseudo-BRT project. It’s a zero-sum game. So long as BRT is getting all the official attention our side is side-lined in the public’s eyes.

It’s been pointed out here that the likelihood of funding I-35 “Super BRT” through a public bond vote would be much less likely than is the case with LRT, which would run where people actually live and work. One of our most potent arguments is that high ridership depends on convenience and flexibility in options for future build-out/expansion. Yet “Super BRT” on I-35 is just a one-trick route, with few options for east-west routes. In contrast, LRT of course has many possibilities for eventual expansion.


Rendition of LRT on Drag from 2000. Graphic: Capital Metro, via Light Rail Now.

Rendition of LRT passing UT campus on Guadalupe St. An initial starter line in Guadalupe-Lamar corridor would provide basic urban rail backbone for expansion into a citywide system. Graphic: Capital Metro, via Light Rail Now.


This is the sort of discussion that Capital Metro should be facilitating as part of the Project Connect planning process. One bright spot I have seen recently in the process is the agency’s stated intention to respond on their website to written comments. This is an opportunity to find out how responsive the agency is to public interest and demands for specific proposals. At least Capital Metro has not so far ruled out anything.

Thus it is up to pro-rail transit advocates to submit written comments. It’s critical that the written public record reflect the breadth and depth of support for options on the table for consideration. Strong and persistent demonstrations of support for a G-L LRT starter line project may persuade Capital Metro to rethink some of their assumptions and give supporters of this plan a fair hearing, and a detailed response.

This would also be helpful in familiarizing more Austinites with the G-L LRT plan and the case that can be made on its behalf. Advocates of LRT – including the starter line LRT project in the Guadalupe-Lamar corridor – have sufficient expertise and numbers behind this proposal to present a credible and persuasive concept that will be difficult to dismiss.

So long as positive expressions of support are received the transit agency must recognize the breadth and depth of support for urban rail. Hopefully some official heads can be persuaded.

Advertisements
h1

Urban Rail on Guadalupe-Lamar, Not I-35 “BRT”

31 July 2017

Map from Austin Rail Now/Our Rail leaflet distributed at July 26th “Traffic Jam” shows 21-mile light rail transit line proposed as a “high-capacity transit” alternative to the “BRT” line in I-35 advocated by TxDOT and other road proponents.

As our April 30th article «Reorganized Project Connect 2.0 opens up, reaches out» explained, Project Connect – the major planning effort -sponsored by Capital Metro, has been re-evaluating Austin-area corridors as possible candidates for rail and other forms of “high-capacity transit”. In recent months, the Texas Department of Transportation (seeking funding participation for its planned overhaul of Interstate Highway 35 through Austin) has been prodding the transit agency to allocate funding for a so-called “bus rapid transit” (BRT) service to be installed in the proposed reconstructed highway. This has become one of the de facto “high-capacity transit” alternatives competing with urban rail in the Guadalupe-Lamar corridor for major local funding.

On July 26th, Project Connect, Capital Metro, and several other collaborating agencies sponsored a “Traffic Jam” community meeting, with invited panelists, to discuss possible options in the planning process. The following article is adapted from a leaflet published and distributed by Austin Rail Now, together with the Our Rail political action committee, at the “Traffic Jam” meeting, focusing on a proposed central 21-mile light rail transit (LRT) project, paralleling I-35 and Loop 1 (“MoPac”, Austin’s other north-south freeway), as an alternative to the I-35 “BRT” proposal.


Why not a true mobility option?

Alternative to I-35 and Loop 1 — A 21-mile urban rail line, running from Tech Ridge in the north to Southpark Meadows in the south, following the Loop 275 (North Lamar to South Congress) corridor, could provide alternative traffic relief to Austin’s major north-south freeways (I-35 and Loop1/MoPac).

Map at left illustrates the major neighborhoods and activity centers that would be served. Such a route could plausibly have a potential of attracting ridership of 100,000 a day.

Better option than I-35 “BRT” — Urban rail is a far better public transit option than a dubious, seriously handicapped “bus rapid transit” (BRT) line in I-35. Urban rail lines have demonstrated significantly greater potential to attract riders, guide adjacent development, improve commercial taxbase, and stimulate economic activity. It’s unlikely that buses running in an I-35 HOV toll lane would yield any of these benefits.

Affordable — Light rail transit (LRT), predominantly surface-routed, can most easily and affordably be installed to serve people where they live, work, and need to go. Decades of experience in other major U.S. cities demonstrates that light rail is substantially less costly to operate per passenger-mile than buses, and tends to create high-value taxbase around stops. This can significantly enhance public revenue for better city services, while at the same time helping stabilize or even lower property taxes.

Guadalupe-Lamar starter line — Guadalupe-Lamar (G-L) is the center city’s 3rd-heaviest north-south corridor. In addition to major activity centers, the corridor serves a variety of dense, established neighborhoods, including the West Campus with the 3rd-highest population density in Texas. With Austin’s highest total employment density on Guadalupe-Lamar, an urban rail line could serve 31% of all Austin jobs.

An initial 6 or 7 mile LRT starter line from U.S. 183 or Crestview to downtown could serve as the initial spine of an eventual metrowide system, with branches north and south, northwest, northeast, east, southeast, west, and southwest.

BRT Reality Check — So-called “BRT” operations in other cities like Minneapolis and Cleveland typically fail to meet the ridership and urban benefit claims of their promoters. Minneapolis’s Orange Line, an upgrade of the city’s heaviest bus transit corridor in I-35W, with just 14,000 daily ridership on 25 routes after 45 years’ worth of facility investment, is no model for Austin. (In contrast, Minneapolis’s 2 LRT lines attract ridership of 68,000.) Cleveland’s Health Line carries ridership of 16,000 in the city’s historically busiest local corridor. Running both in reserved lanes and in mixed traffic, this line is more akin to Austin’s MetroRapid bus services than a “BRT” operation in I-35.

Community benefits — Compared with buses, LRT systems are more user-friendly, more comfortable to access and ride, and more reliable. G-L LRT would provide higher passenger capacity than the proposed I-35 “BRT”, while being more energy efficient, encouraging denser development and safer, more livable urban environments, and emitting less greenhouse gases.

h1

Another possible design for light rail in Guadalupe-Lamar corridor

30 January 2016
Guadalupe St., near W. 28th St. Graphic: Google Street View.

Guadalupe St., near W. 28th St. Graphic: Google Street View.

As Austin Rail Now has repeatedly pointed out, there are various ways that a starter light rail transit (LRT) line could be fitted workably into the Guadalupe-Lamar corridor. In our December 2014 article «San Francisco’s N-Judah Muni Metro line shows design option for light rail in Austin’s Guadalupe-Lamar corridor» we suggested a design alternative with the objective of inserting dedicated LRT lanes while minimizing disruption and cost and maintaining four traffic flow lanes. In this, we showed how a San Francisco LRT design could serve as a model for installing a dedicated LRT alignment in the relatively narrow 80-foot width of the Guadalupe-Lamar corridor (see illustrations below).


Muni Metro light rail

San Francisco’s N-Judah LRT line could serve as design model for Austin’s Guadalupe-Lamar corridor. Photo (copyright) Eric Haas.


Cross-sectional diagram

ARN’s proposed design shows how LRT, plus 4 traffic lanes and pedestrian/bicycle facilities, could be fitted into relatively narrow Guadalupe-Lamar corridor. Graphic: ARN. (Click to enlarge.)


This past December, another design proposal was made public by Austin community urban activist and Guadalupe-Lamar rail transit supporter Andrew Mayer. Compared to Austin Rail Now’s relatively minimalist approach, Andrew’s design is considerably more ambitious — with undoubtedly more urban impact and capital expense — but it embodies good ideas and hints at the kind of range of optional approaches available to ensure that LRT will work in this key central corridor.

As Andrew explains, “For those who are interested in urban rail along Guadalupe and Lamar … I made a bunch of detailed cross-sections with streetmix several months ago.’ These are posted on the Imgur online image sharing community and image host site: http://imgur.com/a/gsa2n. In this post, we’ll illustrate Andrew’s proposal with sample graphics selected excerpted from his presentation. (Occasional stations are selected to illustrate typical proposed station design.)

Complete Streets approach

While almost any design proposing insertion of dedicated lanes for LRT into this corridor would represent to some extent a Complete Streets approach, Andrew’s proposal seems to be a particularly large-scale and aggressive implementation. As he elaborates,

I feel like these designs are relatively ambitious (2 transit lanes, 4 auto lanes, 2 separated bike lanes, 2 12 ft sidewalks along most of its length), but revamp Guadalupe and Lamar into more complete streets, while seeing if I could retain the existing number of auto lanes. Some of these ideas I came up with way back in 2009 (i.e. the split direction of traffic along west campus, the wide boulevard between 38th and 51st st), some are more recent.

Regardless how much you agree or disagree with these designs, I hope this contributes to the discussion of rail on Guadalupe/Lamar, as I feel like detailed discussion of street design is warranted if there is going to be a push to get [Guadalupe/Lamar/Congress] urban rail on the ballot as soon as possible.

Illustrating this approach is Andrew’s proposal for making the Drag more hospitable to LRT, pedestrian, and bicycle traffic by moving southbound traffic off of Guadalupe and onto either Nueces or “possibly” San Antonio St. (see map below). Andrew notes that “Relatively slow traffic (25 mph) due to traffic calming measures … makes street pedestrian friendly despite higher traffic volumes.”


Map snippet shows Guadalupe St. at right (east), with University of Texas campus bordering on east side; San Antonio and Nueces St. in West Campus neighborhood (west of Guadalupe). Graphic: Google Maps. (Click to enlarge.)

Map snippet shows Guadalupe St. at right (east), with University of Texas campus bordering on east side; San Antonio and Nueces St. in West Campus neighborhood (west of Guadalupe). Andrew Mayer’s design proposes moving southbound traffic from the Drag onto either Nueces or San Antonio. Graphic: Google Maps. (Click to enlarge.)


Proposed southbound traffic moved from Guadalupe to Nueces St. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed southbound traffic moved from Guadalupe to Nueces St. Graphic: Andrew Mayer. (Click to enlarge.)


The Drag (West Campus)

As illustrated below, Andrew’s proposal for the main Drag segment (bordering the West Campus neighborhood) seems to envision dedicated LRT lanes occupying the west side of the street (former southbound lanes, with traffic now moved to either Nueces or San Antonio St.). Traffic lanes are narrowed to 10-ft width. Andrew comments: “Bike lane stays pretty much the same, but the parking lane and current southbound lanes are used for transit lanes. Northbound lanes are pushed slightly westward to allow for a separated bike lane and wider sidewalk.”


Proposed LRT alignment along Drag. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed LRT alignment along Drag. Graphic: Andrew Mayer. (Click to enlarge.)


In this proposal, space for station platforms appears to be appropriated from pedestrian/bike space. It’s not explicit in Andrew’s design, but station platforms would likely be staggered across intersections (a common space-conserving technique in LRT design). Andrew also suggests that “platform” space might be allocated to use as a turning lane for motor vehicles (although this could conflict with the need for a station platform at that same point). Another option, deployed in Houston Metro’s MetroRail LRT design, is to allow a turn lane to share the LRT track (with traffic signal control coordinated with train movements — discussed briefly in our article «Houston’s MetroRail shows the way — How to fit urban rail into Austin’s Guadalupe and Lamar»).

Andrew comments that “In this design, there are two platforms and both open on the right side of the vehicle.” Andrew also suggests the possibility that “the idea was that some buses would also use the transit lanes (i.e. 803, 3, other bus lines that feed onto Guadalupe) and thus the right-hand platforms would be compatible with buses that only have doors on the right-hand side.” However, while sharing of lanes between buses and LRT is entirely possible and done in some situations, sharing where there is high-frequency service by both modes is not advisable. (Our own design proposed center-street running with allocation of at least a single curbside lane on each side for local bus access.)


Proposed 24th St. station (southbound direction). Graphic: Andrew Mayer. (Click to enlarge.)

Proposed 24th St. station (southbound direction). Graphic: Andrew Mayer. (Click to enlarge.)


Proposed LRT alignment on Drag at 24th St., with possible turning lane. Graphic: Andrew Mayer.(Click to enlarge.)

Proposed LRT alignment on Drag at 24th St., with possible turning lane. Graphic: Andrew Mayer.(Click to enlarge.)


Between 24th and 29th St. (Andrew calls this the North Drag), Guadalupe narrows somewhat, constricting the space for LRT as well as pedestrian and bike facilities (see streetview at top of post, and aerial view, below). Andrew’s solution is to rely on the fact that southbound traffic has been re-routed to other streets; he also narrows the sidewalks and assumes that the bicycle route can be re-routed through this section to an available parallel street (Hemphill Park).


Aerial view of most constricted section of Guadalupe-Lamar corridor, between 24th-29th St. Graphic: Google Earth. (Click to enlarge.)

Aerial view of most constricted section of Guadalupe-Lamar corridor, between 24th-29th St. Graphic: Google Earth. (Click to enlarge.)


Proposed LRT alignment in narrow segment of Drag between 24th-29th St. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed LRT alignment in narrow segment of Drag between 24th-29th St. Graphic: Andrew Mayer. (Click to enlarge.)


Central Guadalupe segment

To insert the LRT alignment in the relatively narrow segment of Guadalupe between 29th and 38th St., Andrew’s option seems to eliminate a traffic lane, although he assumes a turning lane in some cases. (With ROW assumed at 100 feet or more, Andrew’s plan would seem to require additional property acquisition in this section.)


Proposed LRT alignment in narrow segment of Guadalupe between 29th-38th St. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed LRT alignment in narrow segment of Guadalupe between 29th-38th St. Graphic: Andrew Mayer. (Click to enlarge.)


Proposed 34th St. station (platform for southbound direction shown). Graphic: Andrew Mayer. (Click to enlarge.)

Proposed 34th St. station (platform for southbound direction shown). Graphic: Andrew Mayer. (Click to enlarge.)


At West 38th St. (shown in a Google Street View below), Andrew apparently proposes a short subway section, commenting “The transit lanes plunge beneath the street in a shallow cut-and-cover tunnel (basically an underpass) so there can be turning lanes for NB auto traffic without expanding the road’s ROW [right-of-way]….” Technically, this is possible — but quite an expensive feature, particularly since a station for this important east-west arterial would certainly be justified (and a subway station would add a considerable capital expense).


Street view of Guadalupe at 38th St. intersection. Graphic: Google Street View. (Click to enlarge.)

Street view of Guadalupe at 38th St. intersection. Graphic: Google Street View. (Click to enlarge.)


Our own design (which avoids any heavy civil works) assumes that LRT, like MetroRapid buses and ordinary traffic, would simply continue to operate through the W. 38th St. intersection at-grade, following the current surface street profile. Nevertheless, Andrew’s tunnel proposal indicates that there are indeed other options in the planning toolbox that could be considered to address engineering, political, or other concerns.

North of W. 38th St., for about eight blocks (to W. 45th St.) this section of Guadalupe is bordered on the east by leafy established neighborhoods such as Hancock and Hyde Park, and on the west by the publicly owned State of Texas property of the Department of Mental Health and Mental Retardation (MHMR, including the Austin State Hospital). Andrew proposes that a narrow strip of this public property be allocated for widening of the Guadalupe ROW, thus facilitating an LRT alignment: “Between 38th and 45th St, about 15 feet of feet from the [public property] is acquired to expand the ROW to 120 feet, allowing for an 2 bike lanes, 2 transit lanes, 4 auto lanes, and a parking lane or left turn lane, and 2 10 ft sidewalks.” Andrew suggests such a transfer of state land to the city would be plausible and workable “because the existing space is basically used for fields, some interior roads, and power lines, all of which can be moved/replaced relatively easily.”


Aerial view of section of Guadalupe St. between 28th-45th St., showing MHMR bordering on west and established residential neighborhood on east side. Graphic: Google Earth. (Click to enlarge.)

Aerial view of section of Guadalupe St. between 28th-45th St., showing MHMR bordering on west and established residential neighborhood on east side. Graphic: Google Earth. (Click to enlarge.)


Proposed LRT alignment in segment of Guadalupe between 38th-45th St. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed LRT alignment in segment of Guadalupe between 38th-45th St. Graphic: Andrew Mayer. (Click to enlarge.)


Use of this property in this manner as part of an LRT alignment has been proposed in various studies and propositions over the past 25 years. The day is surely coming when the State will seek to divest itself of this property, perhaps to private interests, so if an easement for ROW expansion is to be procured, official planning and action would seem urgent. Yet no public body, particularly neither Capital Metro nor the City of Austin, has taken a single official step toward this goal in all the years the idea has been on the table.

In the section north of W. 45th St. West Guadalupe St. branches off Guadalupe to connect with N. Lamar Blvd., forming the Triangle area (see map below). West Guadalupe provides a wider ROW here, and is followed by the LRT route, as shown in Andrew’s design, also below. Andrew comments that “Like in the 38th-45th portion, state land would be acquired (basically fields) to expand the roadway. In this case, the northbound auto and bike lanes would be just east of the existing oak trees next to Guadalupe.”


Map snippet shows West Guadalupe St. joining North Lamar at triangular land section now known as "the Triangle". Graphic: Google Maps. (Click to enlarge.)

Map snippet shows West Guadalupe St. joining North Lamar at triangular land section now known as “the Triangle”. Graphic: Google Maps. (Click to enlarge.)


Proposed LRT alignment past Triangle, with station. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed LRT alignment past Triangle, with station. Graphic: Andrew Mayer. (Click to enlarge.)


North Lamar segment

Having transitioned to North Lamar, the alignment with Andrew’s proposed design would seem to require acquisition of more ROW to accommodate a cross-section width of 115 feet for pedestrian and bike facilities, landscaping, and buffer zones (see typical cross-section, below).

As Andrew subsequently explains,

The expanded roadway would work by turning the parking spaces in front of businesses into larger sidewalks and bike lanes. Parking lanes would be put in between the auto lanes and bike lanes where possible to allow for some parking capacity. I HIGHLY recommend doing a study of the traffic going to businesses along this section of N Lamar. How many customers can access the business by foot/bike/transit? For those who have to drive, is there enough parking on the street or behind the business?

Andrew notes that “Interestingly, this section of Lamar Blvd is one of the study areas for CodeNEXT [current process revising Austin’s land-use regulations], so perhaps there is data available there.”

Andrew’s wide streetscape design (which undoubtedly would require extensive and costly adjacent property acquisition) contrasts with our own narrower design proposal which assumed insertion of LRT within existing public ROW (except at intersections with stations, where modest widening would occur). There’s no question that widening North Lamar with amenities such as Andrew has suggested would create a significantly enhanced environment for the public. The issue here is whether it should be included in the initial starter line design, or proposed as a later major upgrade to the corridor.


Proposed typical LRT alignment in North Lamar. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed typical LRT alignment in North Lamar. Graphic: Andrew Mayer. (Click to enlarge.)


For a station at the intersection of North Lamar with the major east-west arterial Koenig Lane (shown below), Andrew remarks that “Large parking lots in the shopping center, unused TxDOT land (that was going to be used for freeway along [Koenig] Ln), and fields along the DPS building could all be acquired to make a full-sized boulevard next to [Koenig] Ln.”


Proposed Koenig Lane station (platform for northbound direction shown). Graphic: Andrew Mayer. (Click to enlarge.)

Proposed Koenig Lane station (platform for northbound direction shown). Graphic: Andrew Mayer. (Click to enlarge.)


Andrew’s designs terminate at Crestview — a major and rather complex nexus, with the heavily used Airport Blvd. intersecting and the MetroRail Red Line rail transit route crossing North Lamar, parallel to Airport (see aerial view, below). Maintaining a 115-ft ROW assumption, Andrew provides a surface LRT design, shown further below; although an interchange station would be essential here, none is presented. Calling his surface design “Alternative 1”, Andrew explains that “Transit lanes stay at grade, there are only 2 instead of 3 NB auto lanes, and the sidewalks are only 12 ft wide each.”


Aerial view of complex intersection of North Lamar with Airport Blvd. and Red Line alignment. Graphic: Google Earth. (Click to enlarge.)

Aerial view of complex intersection of North Lamar with Airport Blvd. and Red Line alignment. Graphic: Google Earth. (Click to enlarge.)


Proposed typical LRT alignment at Crestview. Graphic: Andrew Mayer. (Click to enlarge.)

Proposed typical LRT alignment at Crestview. Graphic: Andrew Mayer. (Click to enlarge.)


Andrew also proposes an “Alternative 2” in which “Transit lanes and the station go into a cut-and-cover tunnel beneath the auto lanes.” He acknowledges that such a subway would be “More expensive and complex to construct, but retains the same number of NB auto lanes and allows for wider sidewalks and more parking.” Andrew indicates a preference for his first alternative, keeping LRT on the surface.

Austin Rail Now believes that an initial surface starter LRT line could safely and efficiently operate through the Crestview intersection as it basically exists. Ultimately, however, some method of grade separation at this complicated intersection may be prudent. We believe this should involve either tunneling or elevating (or both) the motor vehicle trafficleaving the surface to transit, pedestrians, and bicycles. Not only is this approach more compatible with a livable, walkable environment, but it also recognizes that there is many times greater funding available, from all sources, for roadways, while transit is strapped for resources.

Summing up

Considering both our own design proposal and Andrew Mayer’s more ambitious approach, our thoughts return to the controversy over Project Connect’s ill-fated urban rail planning process and proposal that emerged through the fall of 2013 and eventually crashed and burned in the November 2014 vote — in particular, the expressions of skepticism, utter hopelessness, deficit of vision, and outright hostile resistance voiced by several members of the Central Corridor Advisory Group (CCAG) and Austin City Council in their efforts to disparage and dismiss the possibility of installing LRT in the Guadalupe-Lamar corridor. Fortunately, that nonsense (whether based on misunderstanding, ignorance, or cynical political sniping) has mostly evaporated.

Between the two designs now already on the table, it’s possible to see that in reality a broad range of alternatives and design options is available to make this happen. It’s neither impossible nor astronomically expensive. We believe our “minimalist” design is the most immediately affordable, workable, and attractive to voters and the public at large — but that’s just our assessment; we strongly believe all options are worth considering.

It’s time to end Austin’s long saga of indecision, conflict, bumbling, bungling, and diddling. Guadalupe-Lamar is truly the city’s strongest “central corridor”, by far the most logical backbone for a light rail transit starter line. The major task at hand is mustering the community and political will to bring an LRT project here to fruition. ■

h1

Dedicated transit lanes on Austin’s Drag must be designed for light rail

29 September 2015
Busy section of Austin's Drag, Guadalupe St. at W. 24th St. Official city planning by CTR has proposed curbside transit lanes, with buses running on outside lanes as seen in this photo. (Screenshot from Google Streetview.)

Busy section of Austin’s Drag, Guadalupe St. at W. 24th St. Official city planning by CTR has proposed curbside transit lanes, with buses running on outside lanes as seen in this photo. (Screenshot from Google Streetview.)

By Lyndon Henry

The following commentary has been adapted and expanded from remarks posted to an online Austin rail discussion. Lyndon Henry is a transportation planning consultant, a technical consultant to the Light Rail Now Project, an online columnist for Railway Age magazine, and a contributing editor to Austin Rail Now. He is also a member of the Light Rail Technical Forum and Streetcar Subcommittee of the American Public Transportation Association (APTA). His comments highlight the vision of Austin Rail Now and other transit advocates that light rail is justified in, and needs to be planned for, a number of the Austin area’s major travel corridors.

As most Austinites are undoubtedly aware, the Drag is that section of Guadalupe St. stretching between (approximately) West MLK Jr. Blvd. and W. 27th St. Straddled by the University of Texas campus on its east side and the high-density West Campus neighborhood on its west side, the Drag is perhaps the single most important segment of the Guadalupe-Lamar corridor. See: «Long saga of Guadalupe-Lamar light rail planning told in maps» and «Dobbs: Density, travel corridor density, and implications for Guadalupe-Lamar urban rail».


Map shows the Drag area (Guadalupe St., running north-south in center). UT campus lies on the east, West Campus neighborhood on the west. (Screenshot from Google Maps.)

Map shows the Drag area (Guadalupe St., running north-south in center). UT campus lies on the east, West Campus neighborhood on the west. (Screenshot from Google Maps.)


Now, driven partly by their fixation to substitute buses for rail as “rapid transit”, and partly by pressure from some community groups and activists, local civic leaders and official planners are floating plans for dedicated transit (read “bus”) lanes on the Drag. (Official planning defines “the Drag” as continuing north to W. 29th St.)

Last month (August 2015), AURA (originally Austinites for Urban Rail Action), a grouping of mostly Millennial-aged urban planning enthusiasts, posted a proposal for major improvements on the Drag, one of which suggested: “Extend transit priority lanes from Downtown to the Drag”.

At peak periods, transit moves roughly half of the people passing through the corridor. This is to be expected in a central location like the Drag, as transit is by far the most efficient way to move people in a city.

Given the anticipated growth of the city, increasing the throughput of people in the corridor is of paramount importance. The city should plan ahead for increased frequency of existing bus routes, and continue to examine the viability of Guadalupe as a future corridor for rail service. Buses should not have their effectiveness limited by less efficient forms of mobility. Two lanes of Guadalupe should be dedicated solely to transit.

Back in May, per its contract with the City of Austin (COA), UT’s Center for Transportation Research (CTR) produced for city staff a memo of its findings with respect to installing dedicated lanes on the Drag. As summarized by AURA’s John Laycock, the report “modeled three scenarios: Scenario 0) the baseline scenario, Scenario 1) a transit lane in each direction on Guadalupe, and Scenario 2) diverting the buses completely off of Guadalupe onto San Antonio.” Laycock reports that the city subsequently requested CTR to model an additional case, involving one transit lane northbound on Guadalupe and another southbound on Nueces/San Antonio. Results from that additional modeling effort apparently have not yet been released publicly.


Diagram from CTR report for curbside dedicated lanes on the Drag. (Screenshot from CTR memo.)

Diagram from CTR report for curbside dedicated lanes on the Drag. (Screenshot from CTR memo.)


The proposal for dedicated transit lanes on the Drag may seem fairly benign, helpful to public transport and innocuous to the prospects for light rail (LRT). However, installing reserved transit lanes without broader planning for rail can raise some quite serious problems. Depending on their design and implementation, transit lanes could significantly improve or seriously impede the prospects for light rail transit (LRT) — by far, the most feasible and affordable rail option — in the Guadalupe-Lamar corridor. (See «Plan for galvanizing Austin’s public transport development: Light rail starter line in Guadalupe-Lamar».)

First, I’ll note that implementing a high-quality bus service as a precursor to rail can be an effective way of building ridership and preparing the public for the coming rail upgrade. Likewise, establishing reserved transit lanes that can be dedicated to rail can also be helpful. However, both infrastructure and configuration of dedicated transit lanes, done improperly, can create problems.

Infrastructure — Proponents of dedicated transit lanes have argued that all that’s needed is to paint some stripes on the street. And certainly, in the scheme of transit capital projects, just “painting” markings on pavement is relatively cheap. But there’s almost always more involved. The Guadalupe-Lavaca transit lanes, for example, included repaving, plus bus stop relocation and upgrading. Parking meters were removed. And the project has resulted in effectively eliminating the possibility of dedicated LRT tracks on those sides of these streets (bus traffic too heavy).


Buses use curbside reserved lanes on one-way Lavaca St. downtown. Curbside lanes on the Drag would be similar, but on two-way street. Photo: L. Henry.

Buses use curbside reserved lanes on one-way Lavaca St. downtown. Curbside lanes on the Drag would be similar, but on two-way street. Photo: L. Henry.


In previous discussions I’ve suggested that LRT dedicated lanes would need to be relocated on the opposite side of each street. Total cost of the downtown bus lane project was about $370,000 — not a billion-dollar investment, but enough of an investment certainly to give pause to totally redoing this project, or making substantial modifications to it (although modification to add LRT would definitely be a highly worthwhile investment).

We also don’t know what COA and Capital Metro have in mind for the Drag project. Some community transit activists might be thinking very minimalist, but what are official planners thinking?

Configuration — The precise alignment on the transit lanes also needs serious consideration with respect to the needs of LRT (and evidence suggests that a substantial portion of the Austin community would like to see LRT as a project on the planning table now). Curbside lanes — as assumed in the CTR design, described above — are used by several major LRT systems (Portland, Houston, Dallas, and Denver come immediately to mind), but this configuration can often encounter serious problems, mainly with motor vehicle right-turns and especially pedestrian traffic (including where the right turns are made). Another problem for the Drag is the number of driveway cuts and the issue of access to businesses along this commercial alignment.


Denver: Passengers waiting to board LRT train running in curbside lane on Stout St. Photo: Peter Ehrlich.

Denver: Passengers waiting to board LRT train running in curbside lane on Stout St. Photo: Peter Ehrlich.


To be sure, a number of different LRT alignment and configuration options are possible. My preferred alignment concept for the Drag has been to keep both LRT tracks on Guadalupe, in the center (with stations also in the center), and the outside (curb) lanes continued for mixed motor vehicle traffic, including buses. The main reason for this configuration is that buses need access to right-side loading at stops, and I envisioned that local routes like #1 would need to be continued. Of course, bus routes could be moved further west, probably to San Antonio-Nueces, but keeping them on Guadalupe would facilitate relatively easy transfers to and from LRT and bus.

Ideally, the main Drag segment in this heavy-pedestrian/heavy-transit traffic area should be converted to a pedestrian-transit mall, with general motor vehicle traffic prohibited (except perhaps in the case of service vehicles for adjacent businesses). However, a design with reserved transit lanes plus a single mixed-traffic lane in each direction would appear to be possible.

To sum up: While dedicated transit lanes, with very minimal investment, could possibly be helpful as a preparation for LRT, I’d recommend huge caution and vigilance as this notion moves forward. Keeping particularly in mind the considerations I’ve raised above.

In this regard, it’s important to realize that a major chunk of Austin’s civic leadership, and planning establishment, still regard MetroRapid as the city’s “rapid transit system”. Likewise, the fantasy persists that Austin could “become the best bus system we can be” without a rail system. (Cities with the “best bus systems” also seem to happen to have excellent rail systems too.) Reserved transit lanes on the Drag could advance the case for LRT, but only if they’re properly configured, designed, and planned in the context of an ultimate LRT outcome. ■

h1

Plan Now for Light Rail in South Lamar!

29 April 2015
South Lamar corridor. Map: City of Austin.

South Lamar corridor. Map: City of Austin.

By Lyndon Henry

The following comments, adapted here to webpage format, were distributed to attendees at a public event sponsored by the City of Austin’s South Lamar Boulevard Corridor Study project on 10 December 2014. Lyndon Henry is a transportation planning consultant, a technical consultant to the Light Rail Now Project, and a contributing editor to Austin Rail Now. His comments highlight the vision of Austin Rail Now and other transit advocates that light rail is justified in, and needs to be planned for, a number of the Austin area’s major travel corridors.

► South Lamar light rail transit line makes sense

• In terms of both travel density and traffic congestion, South Lamar Blvd. ranks high among Austin’s major travel corridors (see Latest TTI data confirm — Guadalupe-Lamar is central local arterial corridor with heaviest travel). Current travel density plus rapidly increasing population density plus commercial growth in this corridor all indicate that planning for light rail transit (LRT) should long since have been under way.

• A South Lamar surface LRT line, possibly using an alignment design such as is illustrated below, needs to be a major part of an eventual citywide system branching north, south, east, and west throughout our region from an initial central spine in the Guadalupe-North Lamar corridor.


Cross-sectional diagram showing how center LRT reservation could be inserted in South Lamar, maintaining traffic lanes and sidwalks. Design would use side-mounted traction electrification system poles for suspending the overhead contact system for LRT electric propulsion. Graphic: ARN. (Click to enlarge.)

Cross-sectional diagram showing how center LRT reservation could be inserted in South Lamar, maintaining traffic lanes and sidwalks. Design would use side-mounted traction electrification system poles for suspending the overhead contact system for LRT electric propulsion. Graphic: ARN. (Click to enlarge.)


• The South Lamar Corridor Improvement Program should be reconfigured to include planning for LRT as a crucial focus of this project. Planners and traffic engineers need to ensure that any “improvements” in this corridor facilitate dedicated transit lanes for future light rail, and certainly should not impose obstacles to it. It’s way past time to scrap the practice of proceeding with major projects with little if any thought to the future.

► Form a Community Policy & Technical Oversight Committee

• Planning should involve the Austin community as a whole, and this means forming a broad, inclusive community committee to oversee policy and technical decisions, including a comprehensive transit-focused mobility plan for Austin and its surrounding region. No more secretive project teams meeting in a virtual “bunker”, then emerging to tell us what they’ve decided for us! Authentic public participation means including representatives of neighborhood and other community groups, plus others with applicable expertise within the Austin community at large.


Current view of traffic on South Lamar. Photo: Austin Mobility.

Current view of traffic and urban development on South Lamar. Photo: Austin Mobility.


► Dedicate street lanes for light rail transit

Light rail can carry many more peak passengers than private cars, and attract many more riders than buses (both “regular” and MetroRapid). Austin needs to start re-allocating street space from traffic lanes to transit lanes, and the South Lamar corridor must be included. Smart design could install LRT in this corridor while retaining at least 4 lanes of traffic (see diagram in first section, above). ■

h1

Stealth plans for “forced busing” in heavy local travel corridors may be wasteful barrier to light rail

30 March 2015
Consequences of investing in bus-based "rapid transit" (BRT) can be seen in Ottawa, where bus bunching and huge bus jams like this one reveal massive size of fleet necessary to support "rapid transit" levels of ridership — ridership far more efficiently accommodated by urban rail . Similar plans for expanded BRT infrastructure in Austin pose similar need for light rail transit (LRT) alternative. Photo: Flickr.

Consequences of investing in bus-based “rapid transit” (BRT) can be seen in Ottawa, where bus bunching and huge bus jams like this one reveal massive size of fleet necessary to support “rapid transit” levels of ridership — ridership far more efficiently accommodated by urban rail. Similar plans for expanded BRT infrastructure in Austin pose need for light rail transit (LRT) alternative. Photo: Flickr.

By Dave Dobbs

Dave Dobbs is publisher of LightRailNow.com. This commentary has been adapted and expanded from original private Email comments.

Recent developments in local metro area transportation planning, particularly in the aftermath of last November’s ill-conceived “urban rail” bond vote debacle, have made it evident to some of us that there’s a need for a grassroots collection of stakeholders to unite behind a new urban rail planning process, and getting it started ASAP. This is more urgent than most people realize.

It’s abundantly clear that, over the past several years, Project Connect and CAMPO planners and officials have been aiming toward “forced busing” on Austin’s best potential light rail routes, the heavy local travel routes where currently the big red MetroRapid buses run — Guadalupe/North Lamar, South Congress, and South Lamar. As I pointed out in an earlier article on this issue («No urban rail on Guadalupe-Lamar? Then get ready for bus lanes…»), it’s ironic that, for the past several years, while some public officials have piously insisted we can’t possibly convert car travel lanes to reserved rail lanes on Guadalupe/North Lamar, it seems that all along, since at least 2012, this has been in planning for MetroRapid — in effect, a “stealth” plan for incremental BRT.


Light rail/urban rail has simply vanished from CAMPO's 2040 Transportation Plan. Screenshot of Urban Transit page: ARN.

CAMPO 2040 plan includes hundreds of millions of dollars in proposed “BRT” projects, including plans to construct dedicated lanes in Guadalupe-Lamar corridor in lieu of light rail. Screenshot of Urban Transit page: ARN. (Click to enlarge.)


If, this coming May, the CAMPO 2040 plan is adopted with the Urban Transit Projects (2020 – 2040) currently in the plan, Capital Metro, perhaps together with the City, will have the green light to immediately pursue federal funding for concrete bus lanes on the above thoroughfares. And they will no doubt do so, as the 80% federal matching funds for buses are far more available than 50% federal matching funds for rail. Yet, even with the heavier federal proportion, this would be a disastrous waste in the longer term, since the ridership attractiveness, cost efficiency, more livable urban environment, stimulus for transit oriented development (TOD) and economic development, and other benefits for the community, far outweigh the advantage of a higher rate of federal bus system funding.


Total cost per passenger of urban rail becomes lower than "bus rapid transit" as ridership rises above about 10,000 per day. Graph: Project Connect.

Project Connect graph, presented in June 2012 to Transit Working Group, showed greater cost-effectiveness of urban rail (LRT) compared with BRT, as ridership increases. Screenshot: ARN. (Click to enlarge.)


We should expect that the MetroRapid bus lane process will be similar to the Project Connect rail public process — i.e., art gallery open houses, boards and commission hearings and approvals, and finally, council and Capital Metro board approval … but no general public vote, because the the local 20% match will be small enough to construct discrete sections and can probably be found in a slush fund someplace. While 20% of the overall $442,861,656 Capital Metro has identified for dedicated MetroRapid bus lanes is around $88.6 million, it’s logical to expect a piecemeal approach, one section at a time, so as to avoid a citywide response over the loss of vehicle travel lanes. Divide and conquer.

For example, after having paint-striped a little over a mile of Guadalupe and Lavaca between Cesar Chavez and MLK, the most likely next step is to convert two vehicle travel lanes on Guadalupe from MLK to the Triangle (North Lamar at Guadalupe), a distance of 2.5 miles, for about $60 million. Of this, Austin’s share would be roughly $12 million, small enough to be found in current budget funds without going to the voters. Perhaps an even shorter segment, 1.5 miles to 38th Street, would be considered, where the local share would be only about $7 million.

While the downtown Guadalupe/Lavaca paint striping cost $270,000/mile, the dedicated lanes called for in the CAMPO 2040 plan are tear-up-the-street, fix-utilities, and pour 18 inches of concrete (very much like installing light-rail-dedicated reserved lanes) and cost about $24 million/mile for a lane in each direction. Of course, once the bus lanes are in, we couldn’t change our minds because (1) we’ll have spent a lot of federal dollars, and switching over to rail anytime soon would not get a hearing from the Federal Transit Administration (FTA), and (2) merchants and residents are not going to easily, willingly, or peacefully suffer urban street surgery twice. Currently the $38 million in Federal grants for MetroRapid in mixed traffic is mostly portable to another corridor (like Riverside, where it would be appropriate), and after seven years, buses are mostly amortized in the eyes of the FTA. Exclusive bus lanes at $350 million is another matter entirely, for something that can’t be moved.


Construction for dedicated bus lanes, rarely shown by "BRT" promoters, is very similar to that for LRT, as this example from San Bernardino demonstrates. Yet effective capacity, ridership attraction, cost-effectiveness, TOD, and other benefits typically fall short of what LRT typically achieves. Photo: Omnitrans.org.

Construction for dedicated bus lanes, rarely shown by “BRT” promoters, is very similar to that for LRT, as this example from San Bernardino demonstrates. Yet effective capacity, ridership attraction, cost-effectiveness, TOD, and other benefits typically fall short of what LRT achieves. Photo: Omnitrans.org. (Click to enlarge.)


Proceeding with major investment in bus infrastructure in Guadalupe-Lamar and other high-travel local corridors is a huge mistake. As I warned in the earlier article cited above, if you would prefer urban rail instead of a major dedicated bus lane project in Guadalupe-Lamar, “it’s essential to speak up and act. Let neighborhood groups and other community organizations know what official plans have in store for this corridor.” It’s also important to communicate to local agencies involved with planning and members of the Austin City Council “that you want to ride urban rail on Guadalupe-Lamar, running in reserved tracks, not just a souped-up bus service weaving in and out of special lanes.” ■

h1

Resume planning light rail in Guadalupe-Lamar!

11 December 2014
Guadalupe St. at W. 24th St., looking south. The Drag, passing one of the densest residential neighborhoods in Texas and busy commercial district, is major segment of high- travel-density Guadalupe-Lamar corridor. Photo: Google Maps Streetview.

Guadalupe St. at W. 24th St., looking south. The Drag, passing one of the densest residential neighborhoods in Texas and busy commercial district, is major segment of high-
travel-density Guadalupe-Lamar corridor. Photo: Google Maps Streetview.

By Lyndon Henry

The following comments, adapted here to webpage format, were distributed to a public event sponsored by the City of Austin’s Guadalupe Transportation Corridor Project on 3 December 2014. Lyndon Henry is a transportation planning consultant, a technical consultant to the Light Rail Now Project, and a contributing editor to this website.

► Guadalupe-Lamar light rail transit starter line makes most sense

• A light rail transit (LRT) starter line for the Guadalupe-Lamar (G-L) corridor has been studied for 40 years, with at least $30 million invested. (Source: AustinRailNow.com) This is a plan that makes sense, and it’s time to move forward with it!

• G-L is Austin’s most central north-south corridor, with by far the heaviest travel and congestion. A starter line from the North Lamar Transit Center to downtown, serving this busy corridor, established neighborhoods, the high-density West Campus, the Capitol Complex, and the central business district, with a branch to the Seaholm-Amtrak development area, is estimated to carry 30,000-40,000 rider-trips a day. (Source: AustinRailNow.com)

Proposed 6.8-mile "Plan B" light rail transit line in Guadalupe-Lamar corridor would have 17 stations and connect  the North Lamar Transit Center at U.S> 183 with Crestview, the Triangle, UT and the West Campus, the Capitol Complex, the CBD, and the Seaholm-Amtrak area. It's projected to serve 3 times the ridership of the Prop. 1 Highland-Riverside rail line at slightly over half the capital cost.

6.8-mile starter line, proposed by Austin Rail Now, could launch electric LRT service in the Guadalupe-Lamar corridor for less than $600 million. Proposal includes dedicated lanes for rail, 4 traffic lanes, and sidewalks. Map: ARN. (Click to enlarge.)

• A surface starter line like the one shown at left (6.8 miles) could be installed for less than $600 million. With affordable, cost-effective design, this would become the central spine of an eventual citywide system branching north, south, east, and west throughout our region.

• The Guadalupe Transportation Corridor Project should be reconfigured to focus on development of this long-deferred LRT project, along with the $2.5 million of previous funding for the now-defunct Highland-Riverside urban rail plan, now held by Capital Metro. Re-purpose urban rail planning to focus on light rail transit for G-L!

► Form a Community Policy & Technical Oversight Committee

• Planning should involve the Austin community as a whole, and this means forming a broad, inclusive committee to oversee policy and technical decisions. No more secretive project teams meeting in a virtual “bunker”, then emerging to tell us what they’ve decided for us! Authentic public participation means including representatives of neighborhood and other community groups, plus others with applicable expertise within the Austin community at large.

► Dedicate street lanes for light rail transit

Light rail can carry many more peak passengers than private cars, and attract many more riders than buses, MetroRapid included. Austin needs to start re-allocating street space from traffic lanes to transit lanes, and G-L is the ideal corridor to start in! Smart design could install LRT in this corridor while retaining at least 4 lanes of traffic for most of the route. For more information, check out: http://austinrailnow.com

At Dec. 3rd Guadalupe Transportation Corridor Project public event, project manager Alan Hughes (center, in checkered shirt) discusses project issues over table with Drag corridor maps. At far right in photo is Roberto Gonzalez of Capital Metro's Planning Department. Photo: L. Henry.

At Dec. 3rd Guadalupe Transportation Corridor Project public event, project manager Alan Hughes (center, in checkered shirt) discusses project issues over table with Drag corridor maps. At far right in photo is Roberto Gonzalez of Capital Metro’s Planning Department. Photo: L. Henry.