Why light rail transit is crucial for the Orange Line corridor

28 June 2019

A logical and affordable first step to actually implement a bona fide “high-capacity transit” system in the Orange Line corridor would be a 6.2-mile LRT starter line from US183 to downtown. Map: David Dobbs.

Commentary by David Dobbs

This commentary has been adapted, edited, and slightly expanded from original comments submitted to the Federal Transit Administration in response to Early Scoping for Project Connect’s Orange Line “high capacity” corridor (North Lamar-Guadalupe-downtown). David Dobbs is Executive Director of the Texas Association for Public Transportation and publisher of LightRailNow.org.

Austin, Texas is a line village whose principle population centers are caught between two major north-south freeways that are rapidly approaching maximum capacity and cannot be meaningfully expanded. The Texas Transportation Institute (TTI) states that failure to adequately address Austin’s future mobility in the IH-35 corridor will essentially shut down economic growth by 2035. [1] This approximately 21-mile-long, one-to-three-mile-wide ribbon of urban population has only one continuous north-south travel corridor that can provide sufficient mobility for future residents – and then only if a well-designed electric urban light rail transit (LRT) line is constructed as a surrogate/alternate to IH-35 from Parmer Lane to Slaughter Lane, primarily routed via North Lamar, Guadalupe, and South Congress

This concept – basically, an elaboration of the Orange Line sketched in Project Connect’s Long-Term Vision Plan – is summarized in the linked 5-doc_Dobbs_Objective-2030-Basic-Concept page (PDF). Constructed as surface-running LRT (e.g. Phoenix, Houston, etc.), revenue service could begin in 2030. With a 17 mph average speed, a cross-platform transfer point with the Red Line at the Crestview Station, and major park & ride facilities at each end, such a line could plausibly carry as many as 100,000 daily rider-trips by 2035. Running through the densest sectors of the city, it would serve as a template for dense, mixed-use transit-oriented development (TOD), while at the same time providing excellent access to outlying areas sans the use of automobiles. We estimate the cost of this 21-mile Orange Line at approximately $2 billion in 2019 dollars, a fraction of the cost of expanding IH-35 (see map below).

LRT in Orange Line corridor could link Tech Ridge on the north end to Southpark Meadows on the south. Map: David Dobbs.

As the Objective 2030 Basic Concept page also suggests, a first step toward this 21-mile central route could be a much shorter initial starter line (at substantially more modest cost). Illustrated in red on the map (and in the map excerpt included at the top of this post) is a 6.2-mile Minimum Operable Segment running from the North Lamar Transit Center (at US183) on the north end, south via N. Lamar and Guadalupe (and Lavaca) to a south terminus at W. 4th St. downtown.

The Austin community has spent more than $30 million in planning money over the last 40 years trying to get this essential transportation element built here in the Texas capital – see, for example, FTA’s summary of the 2000 LRT plan. [2] Unfortunately, with mobility worsening and the pace of critical urban decisions speeding up, time is running out. We simply cannot wait for some hypothetical new technology to be developed and become available at some undetermined date in the future. Light rail is the proven alternative world-wide.

References

[1] Mobility Investment Priorities Project Long-Term Central Texas IH 35 Improvement Scenarios August 2013 pp 58-61
http://tti.tamu.edu/documents/TTI-2013-18.pdf

[2[ FTA New Starts/Small Starts Austin, Texas/Light Rail Corridors (November 1999-& 2000)
https://austinrailnow.files.wordpress.com/2014/05/fta_austin-texas-cmta-light-rail-corridors-new-starts-nov-1999_.pdf

h1

Stealth plans for “forced busing” in heavy local travel corridors may be wasteful barrier to light rail

30 March 2015
Consequences of investing in bus-based "rapid transit" (BRT) can be seen in Ottawa, where bus bunching and huge bus jams like this one reveal massive size of fleet necessary to support "rapid transit" levels of ridership — ridership far more efficiently accommodated by urban rail . Similar plans for expanded BRT infrastructure in Austin pose similar need for light rail transit (LRT) alternative. Photo: Flickr.

Consequences of investing in bus-based “rapid transit” (BRT) can be seen in Ottawa, where bus bunching and huge bus jams like this one reveal massive size of fleet necessary to support “rapid transit” levels of ridership — ridership far more efficiently accommodated by urban rail. Similar plans for expanded BRT infrastructure in Austin pose need for light rail transit (LRT) alternative. Photo: Flickr.

By Dave Dobbs

Dave Dobbs is publisher of LightRailNow.com. This commentary has been adapted and expanded from original private Email comments.

Recent developments in local metro area transportation planning, particularly in the aftermath of last November’s ill-conceived “urban rail” bond vote debacle, have made it evident to some of us that there’s a need for a grassroots collection of stakeholders to unite behind a new urban rail planning process, and getting it started ASAP. This is more urgent than most people realize.

It’s abundantly clear that, over the past several years, Project Connect and CAMPO planners and officials have been aiming toward “forced busing” on Austin’s best potential light rail routes, the heavy local travel routes where currently the big red MetroRapid buses run — Guadalupe/North Lamar, South Congress, and South Lamar. As I pointed out in an earlier article on this issue («No urban rail on Guadalupe-Lamar? Then get ready for bus lanes…»), it’s ironic that, for the past several years, while some public officials have piously insisted we can’t possibly convert car travel lanes to reserved rail lanes on Guadalupe/North Lamar, it seems that all along, since at least 2012, this has been in planning for MetroRapid — in effect, a “stealth” plan for incremental BRT.


Light rail/urban rail has simply vanished from CAMPO's 2040 Transportation Plan. Screenshot of Urban Transit page: ARN.

CAMPO 2040 plan includes hundreds of millions of dollars in proposed “BRT” projects, including plans to construct dedicated lanes in Guadalupe-Lamar corridor in lieu of light rail. Screenshot of Urban Transit page: ARN. (Click to enlarge.)


If, this coming May, the CAMPO 2040 plan is adopted with the Urban Transit Projects (2020 – 2040) currently in the plan, Capital Metro, perhaps together with the City, will have the green light to immediately pursue federal funding for concrete bus lanes on the above thoroughfares. And they will no doubt do so, as the 80% federal matching funds for buses are far more available than 50% federal matching funds for rail. Yet, even with the heavier federal proportion, this would be a disastrous waste in the longer term, since the ridership attractiveness, cost efficiency, more livable urban environment, stimulus for transit oriented development (TOD) and economic development, and other benefits for the community, far outweigh the advantage of a higher rate of federal bus system funding.


Total cost per passenger of urban rail becomes lower than "bus rapid transit" as ridership rises above about 10,000 per day. Graph: Project Connect.

Project Connect graph, presented in June 2012 to Transit Working Group, showed greater cost-effectiveness of urban rail (LRT) compared with BRT, as ridership increases. Screenshot: ARN. (Click to enlarge.)


We should expect that the MetroRapid bus lane process will be similar to the Project Connect rail public process — i.e., art gallery open houses, boards and commission hearings and approvals, and finally, council and Capital Metro board approval … but no general public vote, because the the local 20% match will be small enough to construct discrete sections and can probably be found in a slush fund someplace. While 20% of the overall $442,861,656 Capital Metro has identified for dedicated MetroRapid bus lanes is around $88.6 million, it’s logical to expect a piecemeal approach, one section at a time, so as to avoid a citywide response over the loss of vehicle travel lanes. Divide and conquer.

For example, after having paint-striped a little over a mile of Guadalupe and Lavaca between Cesar Chavez and MLK, the most likely next step is to convert two vehicle travel lanes on Guadalupe from MLK to the Triangle (North Lamar at Guadalupe), a distance of 2.5 miles, for about $60 million. Of this, Austin’s share would be roughly $12 million, small enough to be found in current budget funds without going to the voters. Perhaps an even shorter segment, 1.5 miles to 38th Street, would be considered, where the local share would be only about $7 million.

While the downtown Guadalupe/Lavaca paint striping cost $270,000/mile, the dedicated lanes called for in the CAMPO 2040 plan are tear-up-the-street, fix-utilities, and pour 18 inches of concrete (very much like installing light-rail-dedicated reserved lanes) and cost about $24 million/mile for a lane in each direction. Of course, once the bus lanes are in, we couldn’t change our minds because (1) we’ll have spent a lot of federal dollars, and switching over to rail anytime soon would not get a hearing from the Federal Transit Administration (FTA), and (2) merchants and residents are not going to easily, willingly, or peacefully suffer urban street surgery twice. Currently the $38 million in Federal grants for MetroRapid in mixed traffic is mostly portable to another corridor (like Riverside, where it would be appropriate), and after seven years, buses are mostly amortized in the eyes of the FTA. Exclusive bus lanes at $350 million is another matter entirely, for something that can’t be moved.


Construction for dedicated bus lanes, rarely shown by "BRT" promoters, is very similar to that for LRT, as this example from San Bernardino demonstrates. Yet effective capacity, ridership attraction, cost-effectiveness, TOD, and other benefits typically fall short of what LRT typically achieves. Photo: Omnitrans.org.

Construction for dedicated bus lanes, rarely shown by “BRT” promoters, is very similar to that for LRT, as this example from San Bernardino demonstrates. Yet effective capacity, ridership attraction, cost-effectiveness, TOD, and other benefits typically fall short of what LRT achieves. Photo: Omnitrans.org. (Click to enlarge.)


Proceeding with major investment in bus infrastructure in Guadalupe-Lamar and other high-travel local corridors is a huge mistake. As I warned in the earlier article cited above, if you would prefer urban rail instead of a major dedicated bus lane project in Guadalupe-Lamar, “it’s essential to speak up and act. Let neighborhood groups and other community organizations know what official plans have in store for this corridor.” It’s also important to communicate to local agencies involved with planning and members of the Austin City Council “that you want to ride urban rail on Guadalupe-Lamar, running in reserved tracks, not just a souped-up bus service weaving in and out of special lanes.” ■

h1

How soon to get Austin’s urban rail on track after Nov. 4th?

11 October 2014
Graphic: LifeHacker.com

Either the Highland-Riverside urban rail plan or a Guadalupe-Lamar plan will need several years to be ready for federal approval. Graphic: LifeHacker.com

By Dave Dobbs

How quickly can Austin get another rail proposal on the ballot if Proposition One fails on Nov. 4th? Pass or fail, I think any rail proposition that would be ready for federal funding is at least three years out — i.e., 2018, considering that the new 10-1 council gets up and running early in 2015.

If Proposition One passes, the new council would have to deal with the political mandate of $400 million of road funding — most likely, in Certificates of Obligation (COs). And given the nature of COs, meant for emergencies, not for general obligation (GO) situations, the oxygen in council chambers is going to be consumed as new council members (a) hear from the public pro and con and (b) recognize that large city indebtedness limits their ability to expend funds for many other needed things (particularly their own priorities and campaign promises), while at the same time setting the stage for even more debt for a controversial rail project that will surely necessitate giving up a quarter cent of Capital Metro’s sales tax they now collect.

Assuming that the issue of COs could be settled in a year’s time and the city could begin selling bonds to fund the detailed planning necessary to qualify for federal funding, it will still take two to three years for the federally mandated steps necessary to get back into line for federal funding. Remember, when Project Connect switched the destination from Mueller to Highland, the current project on the ballot lost its place in line. (Council members knew this when they placed Proposition One on the ballot.) Considering that federal funding is highly competitive, with something like 50 U.S. cities doing some kind of urban rail planning in pursuit of federal dollars, Austin’s current project (supposedly with 18,000 daily riders) for $1.4 billion is simply not cost-effective or cost-competitive.

Now if Project Connect still has some funds left from the $5 million allocated from CAMPO’s SMP-MM grant and what the Council provided in 2013, and Prop. One passes, then rail planning for Highland/Riverside could go on while council thrashes about trying to deal with the $400 million in COs. Nonetheless, it would still be 2018 before any Project Connect plan would be ready for federal consideration and the ridership and the project won’t be any better.

If Proposition One fails, then the new 10-1 council will be able to get organized and set its own priorities, one of which would be to disconnect Project Connect, along with its funding, and then assess where the community goes with Capital Metro, transit priorities, rail planning, and what role the city, itself, has in all this. Hopefully, any funding that is left from Project Connect could be held in abeyance until Council agrees to set up a new public study process that has real public input and gives public stakeholders ownership. Right now, Capital Metro has been so poorly used by politicians and the private political agendas the politicians represent, that we need to have a community discussion about what transit’s role is in the future and who does what.

The city and the transit authority, after all, have to agree upon how to use the limited assets we call the public streets. We have to decide whether streets are for people (pedestrians, bikes, and transit) or sewers for cars. While some of our elected officials piously claim we can’t give up automobile travel lanes for rail on Guadalupe and Lamar, the CAMPO plan (its Capital Metro elements) projects dedicated bidirectional busways for MetroRapid on all of the best potential rail routes in the city by 2025.

Overhead view of MetroRail on Main St. at Preston. Photo: Houston Metro.

Houston’s MetroRail light rail transit system runs on dedicated tracks on Main St., re-allocated from traffic lanes. Photo: Houston Metro.

Given the undeniable need, now becoming patently obvious to most of the attentive public, that something must be done in the core along the Guadalupe/North Lamar corridor, the new Council will be under enormous pressure from most of the Project Connect supporters and the loyal opposition pro-rail supporters to begin anew looking at a rail proposal that has the right combination of route, ridership, capital cost, and O&M numbers that gets the most bang for the buck. Again, we’re looking at 2018 before any plan could be completed and eligible for Federal Transit Administration funding.

The difference between passing and failing is, of course, funding — i.e., Austin’s local match for a federal grant. While both Proposition One proponents and the loyal opposition pro-rail supporters agree that a local match is essential, the contention that a November bond failure means “another 14 years” before we can visit the issue again, or that a 10-1 council will be unable to agree on where to begin, are arguments for people with an agenda and those who are flying backward to see where we’ve been. ■

h1

Science seems missing from Project Connect’s “scientific” transit planning

10 February 2014
Project Connect's proposed "high-capacity transit" alternative alignments for "Highland" sector.

Project Connect’s proposed “high-capacity transit” alternative alignments for “Highland” sector.

By Lyndon Henry

This past Saturday, Feb, 8th, I attended Project Connect’s “interactive workshop” event at the Highland ACC site with a specific mission in mind: raising questions to gather information and data. I particularly wanted to refrain from actually providing input into the process, because Project Connect seems to use this type of public feedback as evidence of popular validation of, and acquiescence to, their overall process, methods, and conclusions — and I wanted to avoid that as much as possible. I did strongly encourage other supporters of the Guadalupe-Lamar alignment proposed for urban rail to attend this event if at all possible.

The most recent documents on the topic of the event, as far as I knew, were the “alternative route” maps that Project Connect had made available online, as a PDF:

http://www.projectconnect.com/connect/sites/default/files/Preliminary%20Alternatives.pdf

Through Project Connect’s presentations to the Transit Working Group and Central Corridor Advisory Group, and in other presentations and statements here and there, a multitude of questions had already been raised, and these maps raised even more issues. Much of my curiosity was motivated by unanswered questions associated with the “Phase 1” study process — supposedly a thoroughly “data-driven” study. Indeed, City Councilman (and Capital Metro chairman) Mike Martinez has emphasized that the route profiles selected by the Project Connect team are all based on a highly “scientific” process. So, in my view, it’s entirely valid to seek the “scientific” evidence that supposedly underpins the route alignment choices now being presented for public perusal.

At the Feb. 8th event, I didn’t have an opportunity to raise all my questions or obtain definitive answers to the ones I did raise, but I’m sharing much of what I did learn in this post. I’ll note that I mainly discussed these with a couple of volunteer Project Connect table moderators, and a couple of Project Connect consultants. I’ve categorized these questions into several sub-issues.

“Highland” issues

• The “Phase 1” study projected huge increases in population and economic activity in this sector by 2030. Where, exactly, would these increases occur?

Basically, the Project Connect representatives I discussed this with didn’t have an answer. They’re planning “high-capacity transit” routes on the basis of projections of enormous population and economic growth, but they seemed somewhat confused about whether there was any data indicating exactly where in this sector such growth would occur.

So, how could station locations be determined if you don’t know where the heaviest growth will be? Is there huge growth projected west of Red River, along the proposed Duval alignment? They couldn’t say.

• Do the proposed alignment alternatives take the actual locations of population and economic concentration into account? If so, how?

Basically, no — for the same reason as with the previous response.

However, I did overhear one of the consultants explain to another participant (who favored an alignment to the Mueller development area) that Project Connect was giving “major consideration” to the possibility that an alignment serving Hancock Center would “set you up” for an ultimate extension to Mueller.

• Of the routes within the “Highland” sector from the UT campus to Highland/ACC, I-35 is omitted. Yet heavy traffic on I-35 was included as a major factor in swaying the Phase 1 recommendation for this sector. So, why is this major travel artery not included as a possible “high-capacity transit” (HCT) alignment for this sector? Where’s the metrics-based evaluation to eliminate it?

The impression I got from discussing this is that there’s no “metrics-based” evaluation, just a sort of hunch that an alignment in or along I-35 would not be a good idea. So, if traffic volumes on I-35 were a major factor in selecting the “Highland” route, are there any park & ride sites in mind? I was told that the Highland/ACC site would be an excellent location for a P&R facility — and that seems a quite reasonable judgement.

However, there’s been no study of the relative attractiveness of such a P&R to I-35 motorists between access to the UT and core area via the eastern “Highland” routes or the more direct, western route via Lamar and Guadalupe.

• Duval and Red River are both capacity-constricted minor thoroughfares narrowing into 2-lane neighborhood streets. Are these routes appropriate for the mainline of a HCT service, particularly an urban rail alignment?

Project Connect is seriously considering rail on these streets, but other than that confirmation, I couldn’t get any evaluatory comments. One participant mentioned a possible streetcar-type alignment, and another argued that these were “three-lane” streets, which is hard to believe from the visual evidence. (To procure a third lane, you’d have to eliminate neighborhood street parking on Red River and bike lanes on Duval.)

Both Red River (left) and Duval (right) are narrow 2-lane neighborhood streets, with barely space for local parking on Red River and bike lanes on Duval. L. Henry screenshot from Google Maps streetview.

Both Red River (left) and Duval (right) are narrow 2-lane neighborhood streets, with barely space for local parking on Red River and bike lanes on Duval. L. Henry screenshot from Google Maps streetview.

I mentioned that “HCT” by Project Connect’s definition could mean MetroRapid bus service, but I was assured that, for reasons not explained, they have rail in mind for this route.

• To install HCT in these alignments, are property acquisitions for right-of-way (ROW) being considered?

I couldn’t get a clear answer on this.

• For these alignments, are elevated or subway alignments under consideration for urban rail? In the case of a subway, where would the portal be located (this generally takes most of a city block)?

Elevated and subway construction seems to be under consideration only in a very general way; I got the definite impression that Project Connect’s thinking is focused more on a surface alignment. I didn’t have a chance to raise the portal issue.

• Where would a storage-maintenance-operations site for rolling stock be located?

I didn’t have a chance to raise this issue. (Previous urban rail planning tended to locate an SMO facility on the Mueller site, or just north of it.)

• For the alignments along Airport Blvd., wouldn’t these duplicate MetroRail service?

A consultant explained that Project Connect doesn’t see duplication, because the HCT service (whatever it is) would have intermediate stops, unlike MetroRail. Apparently, in their minds, you only have duplication if you duplicate all or most of the parallel line’s stations. I found it rather peculiar that Project Connect planners would regard it as impermissible to replace MetroRapid bus service on Guadalupe-Lamar with urban rail, but quite acceptable to in effect duplicate rail transit service along Airport Blvd. with, possibly, another form of rail transit.

• Is Project Connect planning to replace a segment of MetroRail service with urban rail? If so, how would MetroRail connect from downtown to Crestview?

Apparently they’re not planning to replace MetroRail with urban rail in this phase of planning.

• If Project Connect is planning on FTA funding for urban rail, would this be possible with a line paralleling existing MetroRail service?

As discussed above, Project Connect doesn’t consider such a route along Airport Blvd. as duplicate service to MetroRail. I doubt, however, that — in the case of a major rail investment — the Federal Transit Administration (FTA) would readily agree with this, especially after their recent award of a TIGER grant to upgrade the MetroRail line.

Core area issues

• Various routes are proposed through the core area. On what specific core area metrics analyses are these based?

Project Connect representatives were somewhat confused by this question about core area metrics. Having followed the “Phase 1” HCT study process closely, I never saw evidence of any metrics-focused study of the core area (Core “sub-corridor”, i.e., sector). One consultant offered the University of Texas’s campus plan as a factor in the decision to follow the East Campus alignment along San Jacinto, but I explained that a plan is more like a wishlist, not a metrics-based analysis. I was told that maybe there was some kind of comparison of ridership, cost, etc. between the eastside and westside (Drag/West Campus) alignments, but nobody could produce one.

• Was a data-driven analysis of various alignments, evaluating ridership potential, cost, etc., ever performed for alternative routes through the core area?

Apparently there has been no metrics-based analysis that would guide alignments within the core area. Project Connect basically is taking major activity centers, such as the planned medical school, into account — but this is more based on whim rather than a “scientific” analysis evaluating data-based metrics.

• Was any kind of data-driven analysis of projected demographics, economic activity, etc., ever performed on the core area in the “Phase 1” study?

No, per the answer to the previous question.

• On what “scientific” data metrics-based rationale is the Drag excluded as an alignment through the core area?

Apparently none.

• On what data-driven basis is the crosstown alignment on 4th and 3rd Streets included?

I didn’t have a chance to raise this issue.

“East Riverside” issues

• The “Phase 1” study projected huge increases in population and economic activity in this sector by 2030. Where, exactly, would these increases occur?

As with the responses to similar questions in regard to “Highland” there seems to be no data for this.

• Do the proposed alignment alternatives take the actual locations of population and economic concentration into account? If so, how?

Again, apparently not, as with the previous responses. It would seem that much of the placement of alternatives is based on hunch and whim rather than a “scientific” evaluation of data elements.

• Why have other major potential alignments through this sector, such as Oltorf St., Congress Ave., and S. Lakeshore Blvd., been excluded? All of these were included in the original “ERC” sector in the “Phase 1” study. Is there data-based evidence for singling out East Riverside as the sole alignment?

Again, no one could explain this.

• Project Connect has repeatedly referred to MetroRapid, with buses running in normal general road traffic, as “high-capacity transit”. Why, then, are bridge options being considered for the “East Riverside” area? Could these buses not use existing traffic bridges?

Bridges are being considered for urban rail or possibly special bus-only use. But representatives agreed that, if MetroRapid is HCT, you could have Project Connect’s definition of “rapid transit” fulfilled by running MetroRapid buses in mixed traffic over existing bridges.

h1

Contradicting local official claims, FTA says it “would consider request” for urban rail on North Lamar

1 February 2014
MetroRapid bus (left) and simulation of urban rail (right). Actual FTA view expresses openness to consider replacing MetroRapid service with urban rail in North Lamar corridor. Photo: L. Henry; simulation: COA.

MetroRapid bus (left) and simulation of urban rail (right). Actual FTA view expresses openness to consider replacing MetroRapid service with urban rail in North Lamar corridor. Photo: L. Henry; simulation: COA.

On December 12th, in the course of a contentious meeting, the Austin City Council endorsed Project Connect’s recommendation to pursue “high-capacity transit” in East Riverside and a narrow swath of area mostly northeast of the UT campus, dubbed the “Highland sub-corridor”. (See City Council to Central Austin: Drop Dead.) Present at this meeting was a long queue of critics of the proposal, and proponents of an alternative urban rail route in the “backbone” West Campus-Guadalupe-Lavaca corridor.

Over previous months, Project Connect and its partisans had repeatedly insisted that Capital Metro’s new MetroRapid bus service in the Guadalupe-Lamar corridor – because it was funded by the Federal Transit Administration (FTA) – was an impenetrable barrier to urban rail. In recent days, the argument had intensified, with solemn declarations that even raising the issue of replacing MetroRapid bus with urban rail might so incense FTA that all future federal funding could be jeopardized.

Thus, in this context, earlier in the December 12th Council meeting, anticipating a barrage of criticism over the rejection of the Guadalupe-Lamar corridor, Councilman Mike Martinez (also chairman of Capital Metro) took the opportunity to make a special announcement, evidently intended to steal a march on Guadalupe-Lamar proponents. Word from the FTA had just come in, he intoned, that the agency considered Metro Rapid an absolutely “permanent” investment, and therefore a daunting obstacle to its replacement by rail.

From the City of Austin transcript, the following are Councilman Martinez’s remarks (for readability, edited for spelling, grammar, and punctuation):

I wanted to read a response from FTA that Capital Metro received this afternoon in a meeting with them in Fort Worth. This is an FTA official that … his response to the question about the high-capacity transit that is already going in, the BRT in the Lamar corridor.

His response was: BRT in the North Lamar corridor is a priority transit project. The project was supported by the region through CAMPO. Capital Metro and FTA signed a contract to this effect. FTA sees their investment as permanent.

It is important to consider that there are many demands for federal funds on new starts and small starts [projects]. and FTA made a permanent investment in this [corridor]. If Capital Metro were to come back to FTA and indicate there is a change in priorities or new need in this corridor, Capital Metro, CAMPO and the community would need to go through the entire planning process again to show that urban rail is the highest priority for this corridor.

That to me is a pretty definitive statement from FTA that it would be difficult, if not impossible, to go back through the process and receive new start money in that corridor. They view the current investment as permanent.

City of Austin transcript excerpt with Councilmember Mike Martinez's Dec. 12th remarks on FTA, MetroRapid, and urban rail for North Lamar. Screenshot: L. Henry.

City of Austin transcript excerpt with Councilmember Mike Martinez’s Dec. 12th remarks on FTA, MetroRapid, and urban rail for North Lamar. Screenshot: L. Henry.

While the FTA statement, as read orally, seemed less of a definitive and absolute rejection of an urban rail alternative in the Lamar corridor than Councilman Martinez portrayed it, as it turned out, further examination or evaluation of the statement was not immediately possible because a printed copy was not made available to the public for scrutiny. Instead, it took a Public Information Request by Scott Morris of the Central Austin Community Development Corporation, and over 40 days, before the actual FTA statement was made available, in the original form provided to Councilman Martinez.

The FTA’s views, as communicated orally to Capital Metro’s representative Ken Cartwright, are summarized by Capital Metro in an internal document available by download from ARN. As this document indicates, Capital Metro raised the issue: “We have been approached about the possibility of putting an urban rail investment in the North Lamar corridor where we already have the BRT investment.”

FTA’s oral (“verbal”) response is summarized:

The Austin community decided that bus rapid transit in the North Lamar corridor was a priority and the next need. The project was supported by the region through CAMPO. Capital Metro and FTA signed a contract to this effect. FTA sees their investments as permanent. However, if the Austin community were to come back to FTA and indicate that there has been a change in priorities or a new need in this corridor, FTA would consider the request. Before making this request, Capital Metro and the community would need to go through the entire planning process again to show that urban rail is the highest priority in this corridor. It is important to consider that there are many demands on federal funds for New Starts and Small Starts projects, and FTA has already made a permanent investment in this corridor.

Of particular interest is FTA’s assurance that “FTA would consider the request” for urban rail if Capital Metro and the Austin community were able “to show that urban rail is the highest priority in this corridor.”

FTA's actual statement, summarized in CMTA memo provided to Councilmember Martinez. Screenshot from PDF by L. Henry.

FTA’s actual statement, summarized in CMTA memo provided to Councilmember Martinez. Screenshot from PDF by L. Henry.

Clearly, the FTA’s actual statement on the issue of replacing MetroRapid service with urban rail is considerably more encouraging than the interpretation verbalized by Councilmember Martinez during the highly polemical Dec. 12th City Council debate on rejecting the Guadalupe-Lamar corridor and endorsing Project Connect’s recommendation for a less centrally located route for “high-capacity transit”. This basically corroborates the position expressed by Austin Rail Now.

See:

MetroRapid bus service should be a precursor to urban rail, not an obstacle!

Why the MetroRapid bus project currently is NOT an obstacle to urban rail in Guadalupe-Lamar

Bottom line: FTA’s actual statement offers a far more propitious prospect for FTA support of urban rail in this crucial core-city corridor.