Austin urban rail: Unfortunate revelations from Project Connect’s April 12th “workshop”

14 April 2014
At April 12th "public workshop", attendees watch presentation from Project Connect Urban rail Lead Kyle Keahey. Photo: L. Henry.

At April 12th “public workshop”, attendees watch presentation from Project Connect Urban Rail Lead Kyle Keahey. Photo: L. Henry.

By Lyndon Henry

On Saturday, April 12th, Project Connect held an event they described as a “Central Corridor Public Workshop” at a location on East Riverside Drive. The notice for the event stated that Project Connect team members would be available “to provide an overview of the issues under study, gather input on maps and final alternatives and answer questions. Input gathered from the workshop will help develop potential transit projects for further study.”

Prior to the event, I prepared a number of questions I would like to have answered. I also disseminated these among other Austin public transit activists.

My questions are presented below, followed by feedback — some of it troubling — that I was able to receive from Project Connect personnel.

 


 

• Why are the public (who are expected to vote ultimate approval) being allowed only these rare, occasional, highly constrained opportunities to review and select from a narrow assortment of choices determined by the Project Connect team and officials? Why aren’t the public, through an inclusive community-wide technical committee, being given the opportunity to be involved in reviewing the basic data, interacting with the consultants, and formulating the choices themselves?

One Project Connect representative seemed to recognize the value of “an inclusive community-wide technical committee” in broadening the pool of possible alternative solutions to challenging issues. He suggested that names of possible candidates for such a group could be forwarded to him.

• Why is Project Connect still going through the motions of a purported high-capacity transit “study” to determine alignment and mode, and seek CCAG and Council approval for an LPA (Locally Preferred Alternative), when it’s already submitted $1.6 billion of URBAN RAIL projects for inclusion in CAMPO’s 2040 plan — including $275mn already projected for an initial route to Hancock to open in 2020? If URBAN RAIL and its details are already a foregone conclusion, why is taxpayers’ money and the time and effort of CCAG, the City Council, and other bodies being wasted on this?

A Project Connect representative’s explanation (consistent with arguments already reported in a newspaper account) was that the “urban rail” data were submitted as “placeholders” in CAMPO’s preparatory process for its 2040 regional transportation plan. However, since Project Connect has supposedly “zeroed out” its previous urban rail plans for central Austin, and within the current “high-capacity transit” study process no mode or specific alignment has yet been formally determined, why were specific “urban rail” projects inserted as “placeholders”, and not a more generic “high-capacity transit” designation? “That’s a good question” was the response.

The dollar amounts were described as mere “updates” of previous Project Connect cost estimates from approximately 2012. But at that time, no “Hancock-Highland” route was planned, so where did the $91.4 million cost for this segment come from? This was “another good question”.

• Why is $190mn in “BRT” infrastructure being proposed for Guadalupe-Lamar? Won’t this be a barrier to future urban rail?

Including $12.9 million allocated to “BRT” infrastructure on Guadalupe and Lavaca, the total for Guadalupe-Lamar “BRT” amounts to $202.9 million. A Project Connect representative was unable to say what specific infrastructure items this included, nor whether these would present a physical barrier to future urban rail.

• Why is a Guadalupe-Lamar route omitted from the $1.6bn urban rail submission to CAMPO’s 2040 plan?

I didn’t have a chance to raise this question directly, but a Project Connect representative insisted that urban rail as well as “BRT” and possibly other modes would be evaluated for future needs in this corridor.

• Why is this plan proposing a slow, tortuous, meandering route from downtown, the least active part of the UT campus, and Hancock Center, to ultimately reach Highland/ACC? Where’s evidence of the travel demand in this route? Does this route carry as much travel as the Guadalupe-Lamar corridor?

The basic responses from a couple of Project Connect personnel at this event seemed to be that the situation has changed since the original “straight and simple” urban rail route in the Lamar-Guadalupe-South Congress corridor was proposed in 2000. Issues of comparative travel demand and ridership weren’t addressed by the personnel. However, several Project Connect representatives seemed to regret that official attitudes no longer favor shifting existing street (and bridge) space from motor vehicle traffic capacity to urban rail.

• What’s the ridership projected for this route? (Wouldn’t that be considered in the decision to submit this to CAMPO?) How can Project Connect claim that this route would have more ridership than the 30,000+ daily ridership previously forecast for the Guadalupe-Lamar route?

A Project Connect representative emphasized that ridership figures for the current proposed line will be forthcoming. But Project Connect representatives seemed to regard previous assessments of the potential of urban rail in the Guadalupe-Lamar corridor as a moot issue.

• Why is a new $75mn bridge proposed to cross Lady Bird Lake, when either the Congress or S. First St. bridge could be retrofitted for urban rail at half the cost or less ($23-36mn)?

Project Connect Urban Rail Lead Kyle Keahey indicated that the option of retrofitting one of the existing bridges was presented to the Central Corridor Advisory Group (CCAG) but was rejected by the group. Accordingly, it has not been pursued further, so the only option has been to propose constructing a totally new bridge.

I pointed out that current officials and selected civic leaders in the CCAG and Transit Working Group (TWG) seem to have adopted a position that retrogresses from the general consensus of 2000 that traffic lanes in streets, arterials, and bridges should and would be reallocated from general traffic to rail transit. Thus, Austin’s leaders appear to have taken a big step backward in their mindset.

• Is a grade separation considered necessary for urban rail to cross the MetroRail line? Why? Dispatching is entirely under the control of CapMetro. Light rail already crosses heavy rail lines in Philadelphia and Tampa. (This issue would also be involved in the case of urban rail on N. Lamar and the MetroRail line.)

According to a couple of Project Connect personnel, because Capital Metro is converting MetroRail to full compliance with Federal Railroad Administration (FRA) heavy rail standards, the unfortunate (and disputable) assessment of Project Connect planners is that urban rail can no longer cross this line at grade, unlike general traffic. This has not specifically been discussed with either FRA or the Federal Transit Administration (FTA), but Project Connect doesn’t want to get involved with the FRA over this. This also means that, according to Project Connect, urban rail will not cross the MetroRail line at grade either downtown or on North Lamar.

I pointed out that this now encumbers any urban rail plan with an extra liability of tens of millions of dollars for constructing grade separations at any future crossing, but Project Connect and civic leaders now seem to exhibit an unfortunate willingness to accept this. The “Highland” urban rail route plan now includes options for tunnels with a cost range of $230 to $290 million for urban rail to access the north side of the MetroRail line and reach Airport Blvd. This would seem to push the total cost of just the downtown-Hancock-Highland/ACC segment close to $600 million (roughly $275 million + $90 million + $250 million).

As I pointed out to several Project Connect representatives, this entire “study” process (post-2004 through the creation of the Project Connect consortium) has resulted in morphing from a simple, relatively straight, affordable surface urban rail route through central Austin’s major activity centers and highest residential densities, with no need for any major civil works, into a meandering, convoluted, complicated route serving more marginal activity centers and less density, and requiring vast expense to build bridges and tunnels.

Urban rail (light rail transit) route proposed in 2000 was much straighter, simpler, cost-effective, and affordable, will no major civil works. Project was approved by majority of City of Austin voters, but failed in Capital Metro service area as a whole. Map: Light Rail Now library.

Urban rail (light rail transit) route proposed in 2000 was much straighter, simpler, cost-effective, and affordable, with no major civil works — and it served central Austin’s heaviest travel needs and highest population density. Project was approved by majority of City of Austin voters, but ballot measure very narrowly (<1%) failed in Capital Metro service area as a whole. Map: Light Rail Now library.

This seems to be the result of errors that are built upon previous errors — in a sense, a process whereby Project Connect is simply digging itself (and the Austin community) into a deeper and deeper hole. Perhaps they’ll begin to understand why I and so many other advocates of public transportation expansion in Austin have become so disgusted not only with Project Connect and its process, but also with the proposals that are emerging from it.

Apparently under pressure from City officials and various civic leaders, the Project Connect process unfortunately also seems to have departed from the goal of seeking a cost-effective, affordable urban rail network for metro Austin. In addition to the other revelations, this was indeed very disturbing. Ideally, the entire Project Connect process would be “reset” back to zero, and a totally new process, embracing once again this goal, would be re-launched.

Possibly, a rejection of Project Connect’s plan and quest for bond funding in November by voters would lead to such a “re-boot” of the urban rail planning process. Otherwise, if this approach to rail development goes forward, it would certainly seem that future rail transit infrastructure expansion in Austin would be severely constrained by the legacy of bad past decisions and design criteria that impose very heavy cost encumbrances.

Advertisement
h1

Average time for rail transit vote to succeed after first failing: 3.8 years

8 April 2014

0_ARN_Ballot-Box-Cartoon-crying-kid

If a proposed rail transit project is rejected by local voters, how long does it take to get voters to approve a subsequent rail project, if one is presented?

According to a study of applicable U.S. cases by the Light Rail Now Project (one of the organizations sponsoring ARN), on average, it takes between 3 and 4 years (i.e., mean delay of 3.8 years). What this means is that — if there’s community will do do so — a new rail transit proposal (typically, a revision of the original one that has failed) can be re-submitted to voters and approved within a relatively short time.

Here in Austin’s “transit war” over competing visions of urban rail, these results challenge contentions of dire consequences (from a possible rail vote loss) being made by partisans of the official Project Connect plan for “high-capacity transit” in a dubious “Highland-East Riverside” route. Rail supporters that perceive major flaws and drawbacks in the Project Connect plan are being advised to swallow their disgust and support the official plan, on the premise that if it fails to win voter support, the development of urban rail would be catastrophically delayed another decade or more, perhaps even forever.

A couple of comments posted online in response to news reports on local media websites give some of the flavor of this line of argument.

See the problem is, if we vote against the urban rail, it will get put off for another ten years. Unfortunately, our fate was sealed when the urban rail committee, who wants the urban rail to eventually go to Mueller, decided upon the San Jacinto/Highland route. We might as well vote for it so that we’ll get some sort of rail closer and more relevant to downtown than MetroRail.
Daily Texan, 3 February 2014

Referring to the Austinites United for Rail Action (AURA) group — many of whose members seems to have misgivings about the official “Highland-East Riverside” route recommendation — another reader, in a comment posted to an article in the Feb. 28th Austin Chronicle, warned

For the good of the city I hope the AURA folks will reconsider their opposition to the likely starter route. With an entirely new district-based City Council taking office in January, November will probably be our last chance at rail for many, many years.

Other proponents of Project Connect’s “high-capacity transit” route recommendation (which currently still doesn’t specify whether it would involve buses or trains meandering along it) have conjured even more dire warnings that urban rail could be stalled for “10 or 20 years or more” if voters fail to pass bond funding for the official plan. For example, in a similar online news site exchange in late February, a commenter identifying herself as a UT development associate argued:

The Federal Government just gave Austin $35 Million for MetroRapid. There is no way they are going to allow us to spend more Federal Money on that route. We have to look forward and make a first step. If we don’t do it now, it’s going to be another 20 years before it’s on the table again. No one wins if we don’t support Project Connect.

The results from the LRN study would seem to debunk these contentions and warnings of doom upon the failure of Project Connect’s plan. LRN explains the methodology used:

To … assess the actual delay between the failure of rail ballot measures and the ultimate passage of support for a subsequent rail transit ballot initiative, the LRN Project team examined available cases since 2000 where an initial rejection of rail was followed by a successful later vote. LRN’s approach has examined this issue strictly from the standpoint of attracting voter support — in other words, if the issue of rail transit is re-voted, how long does it take to win approval?

It should be noted that this study has examined the sequence of events only in cities where, after the failure of an initial measure, a new measure for rail transit (often with a somewhat different plan) was offered to voters. In other cases, poorly prepared or presented rail plans were rejected by voters, but rail planning was subsequently dropped (e.g., Spokane, Columbus) or has proceeded without needing a public vote (e.g., San Antonio).

The study examined six cases, meeting the basic critieria, where such re-votes have occurred — Austin, Kansas City, Cincinnati, Tucson, Seattle, and St. Louis. The analysis indicated that “recent re-votes on rail transit have taken from one to seven years to succeed”, with an average delay of 3.8 years.

In addition, LRN notes that “the data seems to suggest a pattern, whereby the delay before a successful rail transit re-vote is less in cities already operating some form of rail transit (Seattle, St. Louis), in contrast to cities where rail would be a totally new addition to the transit mix (Austin, Tucson, Kansas City, Cincinnati).” Indeed, in the two cities operating some form of rail transit (St. Louis and Seattle), the delay averaged just 1.5 years:

Left bar: Average years of delay in cities already operating rail transit. Right bar: Average delay in cities with no current rail transit.

Left bar: Average years of delay in cities already operating rail transit. Right bar: Average delay in cities with no current rail transit.

While this study “with its very small data set does not offer a basis for strong conclusions” states the LRN report, nevertheless it is possible “to infer that the loss of a vote does not inevitably represent a ‘catastrophic’ setback for rail transit in a given city….” Furthermore, “there is opportunity for plausible speculation….”

• Conditions for a more speedy re-vote and approval of a rail transit ballot measure may be more propitious in communities that already have experience with successful rail transit systems.

• The process of re-submitting a rail transit measure to a vote may depend not so much on public attitudes but on the determination of sponsoring officials, their responsiveness to public input, and their willingness to re-craft specific project details to more closely conform to public needs and desires.