Project Connect’s Austin urban rail would be 3rd-most-pricey LRT starter line in U.S. history
8 May 2014♦
Project Connect’s urban rail plan for Austin, if implemented, at $119 million per mile in current dollars, would be the third most costly light rail transit (LRT) starter line in U.S. history, in terms of cost per mile.
That’s a conclusion Austin Rail Now draws from results emerging from a recent study posted on the Light Rail Now blog, plus other available data. The LRN study, reported in an article titled New U.S. light rail transit starter systems — Comparative total costs per mile, researched the cost per mile of a dozen new “heavy-duty” (as opposed to streetcar-type) LRT starter lines installed since 1990. In 2014 dollars, these range in investment cost from $26.8 million per mile (Baltimore, opened 1992) to $185.6 million per mile (Seattle, opened 2009).
Project Connect’s urban rail proposal
Project Connect revealed their proposal for urban rail (see map below) at a meeting of the Central Corridor Advisory Group (CCAG) on May 2nd. The 9.5-mile project comes with a pricetag of $1.13 billion in current dollars, escalating to $1.38 billion in Year of Expenditure (YOE) dollars by 2020, for a projected ridership in the range of 16,000-20,000 per day.

Project Connect’s proposed line, criticized for avoiding Austin’s central axis and most serious mobility needs, would run 9.5 miles from the Highland site (north) to a terminus on East Riverside (southeast). Map: Project Connect.
The proposal invites comparison with the plan for light rail in the Guadalupe-Lamar corridor (see Austin’s 2000 light rail plan — Key documents detail costs, ridership of Lamar-Guadalupe-SoCo route). When compared, Project Connect’s $1.4 billion plan can be seen to cost 29% more than the previous Guadalupe-Lamar line would cost today, yet provide 35% less route length, and 47% fewer riders.
To finance such a plan through general obligation bonds, according to an April 29th Austin American Statesman report, Austin homeowners would face a substantial increase in property tax, estimated to range between $77 to $153 per year for a “typical” $200,000 home. That estimate was based on financing a $965 million project, about 85% of the actual size of the project now on the table.
Even if the Federal Transit Administration agrees to fund half the project cost, city officials and civic leaders are considering “bundling” the rail proposal with several hundred million dollars for additional road projects. The result could be a substantial 67% increase in Austin’s debt load per capita.
Urban rail cost comparison
At the May 2nd CCAG meeting, Project Connect’s Urban Rail Lead Kyle Keahey assured his audience that the investment cost of the 9.5-mile proposal was quite comparable with recent similar projects, particularly in cost per mile, with the chart shown below as evidence:
However, there’s a serious problem with this comparison — it compares the proposed starter line for Austin with extensions of these several well-established LRT systems, each of them contending with the much more difficult urban and terrain conditions that are typically avoided and deferred in the process of selecting routes for original starter systems. A far more valid cost comparison would evaluate the cost of starter system projects, thus offering better “apples-to-apples” cost equivalence.
That’s because, in designing a starter line — the first line of a brand-new system for a city — the usual practice is to maximize ridership while minimizing costs through avoiding more difficult design and construction challenges, often deferring these other corridors for later extensions. In this way, the new system can demonstrate sufficient ridership and other measures of performance sufficient to convince both local officials and the public that it’s a success from the standpoint of being a worthwhile investment. Thus, comparing the cost of Project Connect’s 9.5-mile project with that of similar U.S. starter lines enables a better evaluation of the Project Connect project in terms of transit industry Best Practices.
Placing the per-mile cost of Project Connect’s proposed line in the cost listing from the recent LRN study affords such a comparison, as shown in the chart below (click to enlarge).
It’s evident from this comparison that Project Connect’s proposed project for Austin would rank as the second most costly U.S. starter line, in cost per mile, since 1990.
But several of these starter lines benefited from the less challenging, lower-cost advantage of being installed in existing railway rights-of-way. Project Connect’s 9.5-mile line would use predominantly paved trackage embedded in existing streets and arterials. Of the new systems tabulated since 1990, only Houston and Phoenix feature comparable in-street alignments.
To evaluate cost in terms of type of type of alignment, Austin Rail Now has compared Project Connect’s proposed line with these other two systems. The results are displayed in the chart below (click to enlarge).
It’s clear that Project Connect’s proposed line is significantly more expensive, in cost per mile, than either of these similarly constructed in-street starter lines in considerably larger urban areas than Austin.
Finally, how would Project Connect’s urban rail plan rank among all U.S. LRT starter lines for totally new systems in the modern rail transit era? By far, the most expensive LRT project has been Buffalo’s 6.4-mile Metrorail line, constructed 81% in subway and opened in 1985. Based on a cost analysis prepared by Alan Hoback for the 2008 Annual Meeting of the Transportation Research Board, the cost of Buffalo’s starter line can be calculated as $228.9 million per mile in 2014 dollars.
Thus, Project Connect’s proposed line, in cost per mile among modern systems, would rank as the third most expensive light rail transit starter line in U.S. history. ■
[…] Read more about this on austinrailnow.wordpress.com […]
I am always impressed by this site and the way it fights for its vision of good LRT. Since I work in the industry, I am always impressed when non professionals can calmly explain their point of view clearly and completely as often as you guys do. However personally, I find it dubious when straight capital costs are compared, even when you adjust for inflation. There are several reasons for this, mostly because when using a single number as a point of comparison it has a tendency to hide many significant factors in that one number. I have a personal rule when doing projects like this. I try to use ranges when ever possible, not single numbers.
I know it is hard to get information sometimes but capital costs with the value adjusted for inflation is only partially accurate. This is because the stated official rate of inflation is usually only 50-67% the real inflation rate that people actually charge in the real world. On top of that, if you go too far back into the past to compare costs you also end up skipping over the periodic increases of minimum wages, periodic spikes in equipment and construction material costs due to changes in safety and work place legislation or supply levels. For example, a government law that banned certain types of insulation back in the early 90’s in the Province of Ontario (where I am from) caused a very large one time spike in the cost of home and commercial building construction while builders had to absorb the extra costs. The builders then passed it on to customers. Simply adjusting for inflation will not explain this.
Lastly, the public can change as well. Calgary’s successful LRT starter line that opened back in 1981 more than likely would not have been built the same way, with the same materials and public expectations if it were built today. A friend of mine who works at Calgary Transit once told me that, the public today simply would not have put up with the same project that started back in the late 70’s. Most likely, extra costs would be added to make up for the fact that today, Calgarians would have simply not put up with all the level road crossings in their starter line compared to the late 1970’s(protected by standard railway crossbucks and baracades). Today they would have demanded more segregation from traffic and thus increasing the relative cost of the line.
I suggest that maybe daily ridership be added to the display, ridership at opening and today’s ridership compared to the expected ridership during planning of the line. Include this with the capital costs adjusted for inflation. Maybe even the theoretical maximum line capacity and the actual real maximum operational capacity. Seattle’s LRT Line for example has a high capital cost but it also has a very high operating capacity compared to most starter lines. Sometimes (although not all the time) you get more when you pay more. Just a suggestion!
[…] route would attract much higher ridership for significantly lower cost. According to a report in the website Austin Rail Now, at $119 million per mile, the Highland-Riverside line would be the third most costly urban rail […]
[…] • Project Connect’s Austin urban rail would be 3rd-most-pricey LRT starter line in U.S. history […]